Open Forum

Shift Field on Timecard

  • 1.  Shift Field on Timecard

    GOLD CONTRIBUTOR
    Posted Feb 13, 2019 04:39 PM
    We have an instance where Finance is not seeing cost in GL or project when Shift is added to a time card with no hours.
    So I am thinking this means that in order for shift to calculate there must be hours on the line.  Need confirmation :)

    TIA!

    ------------------------------
    Karla Johnson
    System Architect
    Schneider Electric
    Carrollton TX
    ------------------------------


  • 2.  RE: Shift Field on Timecard

    BRONZE CONTRIBUTOR
    Posted Feb 14, 2019 09:23 AM
    Karla,

    I would not expect that to work.  The Shift field is used to add to the rate that would otherwise be calculated (e.g. 10% premium for night shift).  If there are no hours to be calculated then the Shift field has no impact.  I have not explicitly tried it, though.

    Mike

    ------------------------------
    Mike Lee
    President
    IT Evolution Management, LLC
    Milliken CO
    ------------------------------



  • 3.  RE: Shift Field on Timecard

    GOLD CONTRIBUTOR
    Posted Feb 14, 2019 11:15 AM
    Thanks Mike!
    Just wanted my thought process to be confirmed :).​

    ------------------------------
    Karla Johnson
    System Architect
    Schneider Electric IT Mission Critical Services, Inc
    Carrollton TX
    ------------------------------